WALLA WALLA — Motorists in Walla Walla face lane shifts and ongoing detours this week as city contractors advance major street reconstruction and bridge maintenance projects.
On the Myra Road Bridge, crews are adjusting bridge approaches through Friday. Officials said lane shifts are in place and drivers should expect delays. The work is part of the city’s preventative bridge maintenance program, which recently saw contractors finish pouring concrete for beam repairs at the Main Street Bridge. Crews will reinstall pavers at that intersection in the coming weeks, while specialized concrete repairs continue beneath a sidewalk on the Second Avenue Bridge.

Main Street bridge work
Meanwhile, substantial construction continues on the Pine Street reconstruction project. Contractors are wrapping up curb and gutter installation between Cayuse Street and Seventh Avenue, while stormwater collection crews push toward Second Avenue. Concrete work will continue next week, with first-phase paving scheduled for next Monday through Wednesday between Cayuse Street and mid-block between Seventh and Ninth avenues.

Concrete at Pine and Nine Avenue intersection
Crews are also building a compact, single-lane roundabout at Pine Street and Ninth Avenue, which is part of State Route 125. The design follows Washington State Department of Transportation policy requiring roundabout evaluations for intersection upgrades. City officials noted safety was a major factor in the selection, citing 14 collisions — including three with injuries — along the corridor over the past three years.
More information is available at https://www.gowallawalla.us/
Top photo: Roundabout concrete work at Pine Street and Ninth Avenue. (All photos courtesy city of Walla Walla)