By Shannon Weidemann (McKone) on Monday, April 4th, 2022 in More Top Stories Northeastern Oregon News
BAKER COUNTY – Crews working on the OR86 Bridge over I-84, the Richland Interchance, will complete drilling holes for anchors this week. This is required for the new concrete bridge rail.
In addition, they will install containment to the opposite side of the bridge for future bridge rail replacement work on that side of the bridge.
There will be intermittent flagging with up to 20 minute delays Monday thru Friday between 7:00 AM and 5:30 PM when necessary for construction activities.
There will be no impacts to traffic flow during non-working hours.