Meacham – (Release from the Oregon Department of Transportation) Work on I-84 from MP241.0 to MP 248.5 this week:

The contractor will continue placing rebar for and paving the new concrete lane all week.  There will be concrete delivery trucks entering and exiting the work zone into traffic, so please use caution when driving through.  Towards the end of next week, the contractor may also start asphalt paving operations.

There will also be some drainage work WB occurring off to the right at approximate MP 247.5 that will require a short WB traffic lane shift that shouldn’t adversely affect traffic.  The EB off and on ramps at the Mt Emily Interchange are open.  The WB off ramp is also open.  The WB on ramp is closed.  Traffic needing to go WB from the Mt Emily interchange will need to get on I-84 EB down to the Spring Creek Interchange, and then get on I-84 WB.

The speed limit remains reduced to 50 MPH through the workzone.