By Garrett Christensen on Monday, October 3rd, 2022 in More Top Stories Northeastern Oregon News
MEACHAM – (Release from the Oregon Department of Transportation) Work on I-84 from MP 241.0 to MP 248.5 this week:
The contractor should be done with place asphalt on the freeway mainline. They will continue to place and spread should rock along the WB shoulder. The contractor will also continue to install guardrail, cut and seal the concrete pavement, and start to lay permanent striping. There will be delivery trucks entering and exiting the work zone into traffic, so please use caution when driving through.
The EB off and on ramps at the Mt Emily Interchange are open. The WB off ramp is also open. The WB on ramp is closed. Traffic needing to go WB from the Mt Emily interchange will need to get on I-84 EB down to the Spring Creek Interchange, and then get on I-84 WB.
The speed limit remains reduced to 50 MPH through the work zone.