College Place City Council approves $2M contract amendment for new water tower project

By on Thursday, December 11th, 2025 in Columbia Basin News More Top Stories

COLLEGE PLACE – The College Place City Council approved Tuesday a contract amendment with JUB Engineers for a new million-gallon water tank and transmission main. The total cost increased from just over $1 million to just over $2 million. The project received state funding for design and construction.

JUB Engineers has divided the project into three parts: Project No. 1 focuses on part of the transmission main related to the Mojonnier Road reconstruction project. Project No. 2 involves the transmission main outside that project, but it still leads to the new reservoir site on Owens Road. Project No. 3 is the construction of the water tower.

The contract amendment includes added costs for landscape design, construction services for projects, and cultural monitoring.

Project No. 2 is set to be bid in early 2026.

Construction drawing via city of College Place