Chip seal project in Baker City

BAKER CITY – Beginning August 16, 2021, the Baker City Public Works Department will be chip sealing a numberof city streets. It is expected that this work will last for four days. The chip seal process extends the life of a street byrestoring vital asphalt pavement components that are lost through the aging and oxidation process. By sealing the street, moisture is unable to penetrate below the asphalt surface. A list of the streets to be treated as well as map showing thestreet locations for the 2021 project are attached.

A minimum 48-hours notice will be provided to residents affected by the street improvement project.

Please expect traffic delays and possible rerouting of traffic during this project. Should inclement weather conditions ormechanical issues arise, the street work will be rescheduled for the next available work day.

Your cooperation and patience during this project are appreciated. If you have any questions, please contact Baker CityPublic Works at (541) 524-2047 or (541) 524-2046

2021 BAKER CITY CHIP SEAL

STREET                      DAY ORDER 
Estes – I I th to I 0th 
Quail Ridge Lane – Indiana Ave to Eagle Crest WaI               2
Nineteenth – Broadway to BakerI                3
Twentifirst – Baker to CampbellI               4
Twentifirst – Broadway to N.side BakerI               5
Resort -S.side A to BI               6
Resort – Campbell to A1               7
Plum- J to L1               8
STREET                      DAY ORDER
Wabash – 4th to 2nd (-int)2
Baker – 9th to 4th (-int)2              2
Baker – I 0th to 9th2              3
Twelfth – Campbell to D2               4
Baker – 21st to 19th (-int)2               5
Broadway – 18th to 17th2               6
STREET                      DAY ORDER  
First – Campbell to B3
Fifth – G to H3               2
Fifth – E to N.side G3              3
Eleventh – Campbell to D3               4
Ohio – 4th to David Eccles3              5
Virginia – 5th to 2nd (-int)3              6